Brevard County building permits come from whichever government controls your address: Brevard County for unincorporated land, or one of the county's 16 cities and towns for property inside municipal limits. That split matters on the Space Coast, because the county, Melbourne, Titusville, and Cocoa Beach each use a different online system and fee method. For a fast first answer, run the free permit checker.
Key takeaways
- Brevard County has 16 municipalities (ten cities and six towns), and your address decides whether the county or a municipality is your starting point for a permit.
- Unincorporated Brevard uses BASS (Brevard's Advanced Service Site), where online permit applications are a feature for registered users with an approved contractor license added.
- Melbourne requires permit applications through its EnerGov online system and prices construction permits on the estimated cost of construction, starting at $65.00 for work of $1,000.00 and less (fees checked November 2026).
- Florida's $7,500 permit exemption does not cover electrical, plumbing, mechanical, structural, or gas work, or property partly or entirely in a flood hazard area.
- A copy of the recorded Notice of Commencement is due before the first inspection when the direct contract is over $5,000, except A/C repair or replacement under $15,000.
Table of contents
- Who issues building permits in Brevard County?
- Which online permit system does my Brevard office use?
- What home projects need a permit in Brevard?
- How much do building permits cost in Brevard County?
- Can I pull my own permit as an owner-builder in Brevard?
- Does the $7,500 permit exemption apply in Brevard?
- When do I need a Notice of Commencement in Brevard?
- What does a re-roof permit look like in Melbourne?
- What should I do before starting a project in Brevard?

Who issues building permits in Brevard County?
If your property is inside a city or town, start with that municipality; if it is in unincorporated Brevard, start with the county. Brevard County's Supervisor of Elections lists the 16 municipalities: the cities of Cape Canaveral, Cocoa, Cocoa Beach, Indian Harbour Beach, Melbourne, Palm Bay, Rockledge, Satellite Beach, Titusville, and West Melbourne, and the towns of Grant-Valkaria, Indialantic, Malabar, Melbourne Beach, Melbourne Village, and Palm Shores, as shown on its municipal officials page.
A mailing address does not always match municipal limits, so confirm your jurisdiction with the permit office before you collect quotes. Our Melbourne permit page gathers that city's forms and fees in one place.
Which online permit system does my Brevard office use?
Each office runs its own system. These are the names each office uses on its own site, checked in November 2026.
| Jurisdiction | Online permit system |
|---|---|
| Unincorporated Brevard | BASS (Brevard's Advanced Service Site) |
| Melbourne | EnerGov |
| Titusville | Online permit application linked from the Building Department page |
| Cocoa Beach | OpenGov |
What can a homeowner do in BASS?
Anyone can search building, development, and enforcement records without registering. Registration is free and needs no contractor license, and registered users can schedule inspections. According to the BASS home page, applying for building permits, paying, and uploading documents are for registered users with an approved contractor license added. If you plan to act as your own contractor in unincorporated Brevard, ask the county how owner-builders should submit.
What home projects need a permit in Brevard?
Most construction, alteration, and repair work needs a permit. Melbourne lists new construction, additions and alterations, fences, driveways, roofing, pools, irrigation, tree removal, and plumbing, electrical, gas, and HVAC work.
Cocoa Beach's list adds A/C or heat system replacements, decks and docks, and hurricane shutters and window replacements. The city says property owners, not contractors, are ultimately responsible for obtaining permits. If your project is not clearly exempt, treat it as permit-required.
How much do building permits cost in Brevard County?
There is no single countywide price, and many offices base fees on construction value. The figures below are copied from each city's published schedule, including Melbourne's Building Permit Fees schedule, checked in November 2026; fees change, so confirm before you budget.
| Fee item | Melbourne (effective August 7, 2026) | Titusville |
|---|---|---|
| Smallest job | $65.00 for $1,000.00 and less | $80 for $0 to $1,000 |
| Mid-size jobs | $65.00 for the first $1,000.00 plus $6.50 per additional $1,000.00, up to $50,000.00 | $100 for the first $2,000 and $6 per additional $1,000, up to $100,000 |
| Plan review | Plan check fee of 50% of the base fee | 50% of the permit fee; re-roof, A/C change-out, window and door replacement, water heater change-out, and fences are exempt |
| Add-ons | 5% technology fee on all Building Division fees | 2.5% state-mandated fee, $4 minimum |
| Re-inspection | $38.00 first, $152.00 after that | $100 |
Melbourne values new construction using current ICC building valuation data or the contracted price, whichever is greater. For unincorporated Brevard, ask the county for its current schedule before you sign a contract. Our guide to Florida permit costs and timelines explains why valuation-based fees vary so much.
Can I pull my own permit as an owner-builder in Brevard?
Yes, if you qualify under the owner-builder exemption in section 489.103(7), Florida Statutes. You act as your own contractor and directly supervise, on site, any work not done by licensed contractors.
- The exemption covers a one-family or two-family residence for your own use that is not offered for sale or lease.
- A sale or lease within one year after completion creates a presumption that you built it for sale or lease.
- You must personally appear and sign the building permit application.
Melbourne posts an Owner Builder form and says the property must be owned by you as an individual and not listed for sale or lease for one year. Read our owner-builder permit guide on the liability you take on.
Does the $7,500 permit exemption apply in Brevard?
Sometimes, for narrow cosmetic work on a single-family home. Section 553.79(1)(g), Florida Statutes, exempts work valued under $7,500, but not on property partly or entirely in a flood hazard area, and not electrical, plumbing, structural, mechanical, or gas work. Splitting a project to stay under the limit is not allowed.
Melbourne handles this through an Exemption Application with a $62.50 exemption request fee. The city says not to start work until the request is approved in writing, and that city ordinance permits remain required regardless of value. See our $7,500 exemption guide for the full test.
When do I need a Notice of Commencement in Brevard?
You need one when the direct contract is greater than $5,000. Florida law has the permit office require a copy of the recorded Notice of Commencement before the first inspection; a direct contract to repair or replace an existing heating or air-conditioning system under $15,000 is excluded.
A Notice of Commencement (NOC) is a document the owner records before work starts so subcontractors and suppliers know who to notify about payment.

What does a re-roof permit look like in Melbourne?
Here is a worked example. A homeowner inside Melbourne city limits hires a licensed roofer to replace a shingle roof for $14,000.
- Confirm jurisdiction. The address is inside Melbourne, so the city, not the county, issues the permit.
- Apply online. The roofer files in EnerGov, because Melbourne requires applications through its online system.
- Find the fee tier. A $14,000 job falls in the $1,001.00 to $50,000.00 row: $65.00 for the first $1,000.00 plus $6.50 per additional $1,000.00. The 50% plan check fee and the 5% technology fee are added on top.
- Record the NOC. The contract is over $5,000, so a copy goes to the city before the first inspection.
- Keep it active. Melbourne says an issued permit expires if no inspection passes within 180 days.
The job is over $7,500, so the exemption does not apply. Our roof permit guide covers inspections and paperwork.
What should I do before starting a project in Brevard?
Confirm your jurisdiction, then confirm the permit list, fees, and forms with that office before you sign anything.
- Check city limits against the 16 municipalities above.
- Find the right portal and register early.
- Ask about flood zones before relying on the $7,500 exemption.
- Vet your contractor's state license and insurance.
- Plan the NOC if the contract is over $5,000.
Skipping a permit costs more later: Melbourne doubles all applicable permit fees when work starts without one.
Our take: Settle the city-or-county question first; it takes minutes and decides everything else. When you cannot confirm that work is exempt, treat it as permit-required, because unpermitted work tends to surface at sale, refinance, or after a storm claim.
When you are ready, check your project in our free tool, then confirm the details with your building department.