Lee County, Florida building permits are issued by Lee County Community Development for unincorporated areas, and by the city, town, or village for property inside an incorporated area such as Cape Coral or Fort Myers. Flood rules shape most Lee County projects, because the 50% rule can require a damaged or remodeled home to meet current flood standards. For a fast first answer, run the free permit checker.
Key takeaways
- Lee County Community Development handles permitting, plan review, and inspections for unincorporated Lee County; incorporated cities and towns run their own permitting.
- Unincorporated Lee charges a $50 application fee and a $35 technology fee per application, plus review and inspection fees, under the schedule effective April 15, 2026 (fees checked November 2026).
- Under the 50% rule, a building in a flood zone whose improvement or repair cost equals or exceeds 50% of the structure's market value must be brought into compliance with current flood regulations.
- Cape Coral says more than 60% of the city is in the Special Flood Hazard Area, so Florida's $7,500 permit exemption will not apply to most projects there.
- A copy of the recorded Notice of Commencement is due before the first inspection when the direct contract is over $5,000, except A/C repair or replacement under $15,000.
Table of contents
- Who issues building permits in Lee County, Florida?
- Which permit portal does my Lee County office use?
- How much do building permits cost in Lee County?
- What is the 50% rule, and how does it affect my project?
- What can I repair after a hurricane without a permit?
- Does the $7,500 permit exemption apply in Lee County?
- Can I pull my own permit as an owner-builder in Lee County?
- What happens with a small remodel in a Cape Coral flood zone?
- What should I do before starting a project in Lee County?

Who issues building permits in Lee County, Florida?
The county issues permits only for unincorporated Lee County, through Lee County Community Development. The county's floodplain page sends residents of Fort Myers, Cape Coral, Fort Myers Beach, Bonita Springs, and Estero to their own jurisdictions. Sanibel runs its own Building Department as well.
To check whether a parcel is unincorporated, the county points to its Resident Information Tool. Our Cape Coral permit page gathers that city's forms and fees.
Which permit portal does my Lee County office use?
Each office runs its own system. These names come from each office's site, checked in November 2026.
| Jurisdiction | Online permit system |
|---|---|
| Unincorporated Lee County | eConnect/ACA (Accela) |
| Cape Coral | EnerGov Citizen Self-Service (CSS) |
| Sanibel | CityView for new permits; EnerGov for existing permits |
| Fort Myers | Self-service portal linked from the city's Permitting button |
Cape Coral takes all permit applications through EnerGov, not at the counter, and expects owner-builders to apply online beginning July 1, 2026. In unincorporated Lee, owner-builders may apply online or in person.
How much do building permits cost in Lee County?
Fees depend on the office. Unincorporated Lee's building permit fee schedule, effective April 15, 2026, adds a $50 application fee, a $35 technology fee, and an operational support fee (a percentage of review and inspection fees) to each application. Cape Coral prints a miscellaneous permit fee schedule effective January 1, 2026. Figures below were copied in November 2026; fees change, so confirm before you budget.
| Residential project | Unincorporated Lee County | Cape Coral |
|---|---|---|
| Re-roof | $25 initial plan review; $100 inspection | No separate re-roof line; the only flat roofing item is "Roofing Miscellaneous: $100.00" (ask the city which applies) |
| Windows, doors, shutters | $35 initial plan review; $50 structural inspection | Window and door replacement: $113.00 |
| Fence | $35 plan review; $25 regulatory review; $50 per required inspection | Fences, residential: $107.00 |
| Re-inspection | $50 per inspection | $48.00 for the first, per discipline |
| Pool | $35 plan review; $25 regulatory review; $50 per required inspection | Swimming pool, residential: $307.00 |
Cape Coral adds a 2.5% surcharge to permits associated with enforcing the Florida Building Code, and a floodplain review costs $55.00 per review. In unincorporated Lee, work started without a permit costs double the total review and inspection fees, with a $200 minimum.
What is the 50% rule, and how does it affect my project?
The 50% rule applies when your building is in a FEMA Special Flood Hazard Area and is not flood compliant. If the cost of improvements or repairs equals or exceeds 50% of the structure's market value, the building must be brought into compliance with current flood regulations, which can mean elevating it.
Substantial improvement is any reconstruction, rehabilitation, addition, or other improvement costing 50% or more of the structure's market value. Substantial damage is damage whose repair to before-damage condition would cost 50% or more of that value.
How does unincorporated Lee measure it?
According to the county's 50% rule page:
- The county uses the Property Appraiser's assessed value of the structure, excluding land. You may submit an appraisal from a Florida licensed appraiser if you disagree.
- Damage repairs are priced at pre-storm rates.
- Plans, surveys, permits, sidewalks, pools, screens, sheds, gazebos, and fences are not counted.
- A substantially improved or damaged building must be elevated to the base flood elevation plus one foot of freeboard.
Cape Coral requires a permit for all improvements and repairs in the Special Flood Hazard Area, including its Substantial Improvement/Substantial Damage application. FEMA's updated Lee County flood maps take effect March 2, 2027. Our flood zone permit guide explains elevation certificates.
What can I repair after a hurricane without a permit?
Very little. Unincorporated Lee's disaster recovery page says anything not on its short list needs a permit first. The list includes debris removal, temporary shoring and bracing, replacing broken glass in existing window and door frames, minor non-structural exterior repairs, and replacing no more than one square (10 by 10 feet) of roof shingles. Substantial damage determinations are made during permit review.

Does the $7,500 permit exemption apply in Lee County?
Rarely, because flood zones are excluded. Section 553.79(1)(g), Florida Statutes, exempts single-family work valued under $7,500, but not on property partly or entirely in a flood hazard area, and not electrical, plumbing, structural, mechanical, or gas work.
Cape Coral says more than 60% of the city is in the Special Flood Hazard Area, so the exemption will not apply to most projects. Eligible owners still apply through the city's online system and pay an administrative review fee, and work may not begin until the city approves the request, per its HB 803 page. See our $7,500 exemption guide.
Can I pull my own permit as an owner-builder in Lee County?
Yes, if you qualify under section 489.103(7), Florida Statutes, for a one-family or two-family home for your own use that is not offered for sale or lease; a sale or lease within one year after completion creates a presumption that you built it for sale or lease. You must personally appear and sign the permit application, and unincorporated Lee says all owner-builders must appear in person to sign documents for issuance. Cape Coral posts an Owner-Builder Disclosure form.
Do I need a Notice of Commencement?
Yes, when the direct contract is over $5,000. A Notice of Commencement (NOC) is a document the owner records so subcontractors and suppliers know who to notify about payment, and a copy is due before the first inspection. A/C repair or replacement under $15,000 is excluded. Our Notice of Commencement guide walks through it.
What happens with a small remodel in a Cape Coral flood zone?
Here is a worked example. A Cape Coral owner of a canal-front single-family home in an AE zone plans $6,500 of new cabinets and countertops, with no plumbing or electrical changes.
- Check the flood zone. The city's Forerunner lookup shows the home is in the flood hazard area.
- Rule out the exemption. The job is under $7,500, but flood zone property is not eligible, so normal permitting applies.
- Apply online. The contractor files in EnerGov with the city's Substantial Improvement/Substantial Damage application.
- Run the 50% check. The city uses that application to compare the project cost against 50% of the structure's market value.
- Record the NOC. The contract is over $5,000, so a copy goes in before the first inspection.
What should I do before starting a project in Lee County?
Confirm your jurisdiction and flood zone first, then fees and forms.
- Check jurisdiction with the county's Resident Information Tool.
- Look up your flood zone and any elevation certificate on file.
- Get a detailed estimate if the work might approach 50% of the structure's value.
- Plan the NOC if the contract is over $5,000.
Our take: In Lee County, find your flood zone before you choose a contractor or a budget. A remodel that crosses the 50% line can turn into an elevation project, and the time to learn that is before work starts, not at inspection.
When you are ready, check your project in our free tool, then confirm the details with your building department.