Duval County Building Permits: A Homeowner's Guide

Jacksonville's consolidated government issues most permits in Duval County, but four beach and rural towns run their own. Here is how to find your office, what permits cost, and how the wind line works.

PermitRoadmap Editorial Nov 17, 2026 12 min read
A single-story brick ranch home in Jacksonville, Duval County, with a shingle roof and tall pines in warm afternoon light

Duval County building permits come from whichever government controls your address. Jacksonville and Duval County operate as one consolidated government, so for most of the county the City of Jacksonville's Building Inspection Division issues permits and inspects the work. The exceptions are four smaller municipalities, Jacksonville Beach, Atlantic Beach, Neptune Beach, and the Town of Baldwin, which run their own building and zoning enforcement. For a fast first answer on your project, run the free permit checker.

Key takeaways

  • In Duval County, the City of Jacksonville's Building Inspection Division issues permits everywhere except Jacksonville Beach, Atlantic Beach, Neptune Beach, and Baldwin, which handle their own.
  • Jacksonville requires online submission for all permit types through JaxEPICS, and you need a JaxEPICS account to submit.
  • Jacksonville's published fees include a window and door replacement rate of $4.00 per $1,000 of construction cost, with a $150.00 minimum when the permit needs one or more inspections (fees checked November 2026).
  • Jacksonville sets its design wind speed by a line running up the St. Johns River and Interstate 95: 125 mph west of the line and 130 mph east of it for typical homes.
  • Florida law requires a recorded Notice of Commencement before the first inspection when the direct contract is over $5,000, except A/C repair or replacement under $15,000.

Table of contents

A homeowner and a contractor reviewing a printed floor plan on the front porch of a brick ranch home in Jacksonville

Who issues building permits in Duval County?

The City of Jacksonville's Building Inspection Division issues permits for most of Duval County. Four municipalities inside the county, Jacksonville Beach, Atlantic Beach, Neptune Beach, and Baldwin, issue their own.

Why Jacksonville and Duval County are one government

Jacksonville is a consolidated city-county government, and its website calls itself the official site of the City of Jacksonville and Duval County. On its commercial permitting page, the city notes that the division's authority is limited to the City of Jacksonville. In practice, a Duval County address outside the four municipalities below goes to Jacksonville.

Which cities run their own building departments?

The same page names the City of Jacksonville Beach, the City of Atlantic Beach, the City of Neptune Beach, and the Town of Baldwin as having their own building and zoning code regulation and enforcement.

Where the property isWho issues the permitHow you apply
Jacksonville (most of Duval County)City of Jacksonville Building Inspection DivisionOnline through JaxEPICS
Jacksonville BeachJacksonville Beach Building Inspection DivisionE-permit applications on the city website
Atlantic BeachAtlantic Beach Building DivisionBSAOnline, including a property owner application
Neptune BeachCity of Neptune BeachCall City Hall at 904-270-2400
BaldwinTown of BaldwinContact the town

Our Jacksonville permit page collects the city's portal, main forms, and fees in one place.

What home projects need a permit in Jacksonville?

Most construction, alteration, and repair work needs a permit. Jacksonville's FAQ lists new buildings, additions such as room additions, patio covers, and pools, alterations such as re-roofs, garage conversions, and exterior stucco, and repairs such as replacing water heaters, A/C units, irrigation systems, new electrical service, and rewiring.

What work does Jacksonville say needs no permit?

The city lists a short set of exempt items:

  • Patio slabs.
  • Replacing plumbing fixtures after the stop, excluding water heaters.
  • Stopping leaks and clearing drain stoppages that do not involve replacing or rearranging valves, pipes, or fixtures.
  • Connecting portable heating, ventilation, and cooling equipment.
  • Replacing any part within a single piece of equipment.

If your project is not clearly on that list, treat it as permit-required. Jacksonville currently enforces the Florida Building Code 8th Edition (2023).

How do I apply for a building permit in Jacksonville?

You apply online through JaxEPICS, Jacksonville's permitting system, which the city requires for all permit types. You need a JaxEPICS account; contractors and design professionals register by emailing a registration form to the division. Owner-builders start in person, as covered below.

What happens after I submit?

JaxEPICS routes your application through a set of reviews, shown as statuses:

  1. DSD and Agency Review. Development Services checks zoning, concurrency, landscape, and drainage, and location can add reviews such as historic preservation or FEMA flood.
  2. Sufficiency Review, then In Review. Once documents are complete and any plan review fee is paid, building and fire plan review begins.
  3. Pending Payment, then Active. After approval and payment, the permit is active and work may begin.

The city's FAQ says to expect 25 to 30 business days for the first review of a building permit, and about 10 business days or less for resubmissions.

How much do building permits cost in Jacksonville?

Jacksonville's fees are set in Section 320.409 of its Ordinance Code and published on the city's City Fees page. Most residential work is priced per $1,000 of cost, per square foot, or per item, with separate trade fees. These figures were checked in November 2026 and the page prints no effective date, so confirm before you budget.

ProjectPublished Jacksonville fee
Window or door replacement$4.00 per $1,000 of construction cost; $150.00 minimum when one or more inspections are required; $25.00 C&D fee per permit
Re-roof$10.00 per 1,000 square feet; $150.00 minimum when one or more inspections are required; $17.50 C&D debris fee
Alterations$3.00 per $1,000 of estimated cost; minimum $112.50 or $33.75 per required inspection, whichever is greater; plan review 67% of the permit fee or $75.00, whichever is greater
Accessory structure up to 150 sq ft and $5,000, no final inspection$45.00 (includes plan review), plus a $15.00 Development Services Fee and $25.00 C&D debris fee
A/C replacement$11.00 per ton for one to ten tons; $60.00 minimum mechanical permit
Water heater$11.00 per fixture, including hot water tanks; $60.00 minimum plumbing permit

Do I need a permit to replace windows or doors in Jacksonville?

Yes. Jacksonville's fee schedule has a dedicated window and door replacement category, and the city publishes a Window and Door Replacement Worksheet for owners who apply themselves. Licensed contractors enter the same information in the Specs tab of the JaxEPICS permit.

How does the wind speed line work?

The worksheet asks for your design wind speed and exposure category, and the city sets the wind line by ordinance (Section 320.103). The line starts in the middle of the St. Johns River at the south end of Duval County, runs north up the river to Interstate 95 at the Fuller Warren Bridge, then follows I-95 north to the county line. For Risk Category II structures, which covers typical homes, the wind speed is 125 mph west of the line and 130 mph east of it.

What the worksheet asks for

For each window, exterior door, and garage door, the worksheet asks for the number of units, size, manufacturer, model, design pressure, and the Florida product approval number including its suffix. A product approval number shows the window or door was tested and approved for use in Florida; our window replacement permit guide explains how to find it.

A worked example

Suppose you own a single-family home east of the line and hire a licensed contractor to replace eight windows and the front door for $14,000. The contractor files a window and door permit in JaxEPICS, listing the 130 mph wind speed, the exposure category, and each product's design pressure and product approval number. The fee follows the $4.00 per $1,000 rate with the $150.00 minimum and the $25.00 C&D fee. Because the contract is over $5,000, you record a Notice of Commencement before the first inspection. The $7,500 exemption does not apply, because the job is valued above it.

A window installer fitting a new white vinyl window into a brick ranch home in Jacksonville under tall pines

Does Florida's $7,500 permit exemption apply in Duval County?

It can, but only narrowly. From July 1, 2026, section 553.79, Florida Statutes, has local governments exempt a single-family owner, or the owner's contractor, from a building permit for work valued at less than $7,500.

The exemption does not apply to:

  • Property partly or entirely in a flood hazard area.
  • Any electrical, plumbing, structural, mechanical, or gas work.
  • A project split into smaller jobs to stay under the threshold.

You must submit a written request with the contract or other documentation showing the work's nature and value. Our $7,500 exemption guide walks through what typically qualifies.

Can I pull my own permit as an owner-builder in Jacksonville?

Yes, for your own primary residence, if it is not for sale or rent and your name is on the deed. Jacksonville requires you to appear in person at the Building Inspection Division, 214 N. Hogan St., Room 280.

The key conditions:

  • You sign an Owner's Affidavit, and improvements to an existing structure also need proof of Homestead Exemption.
  • Licensed electrical, plumbing, mechanical, and roofing contractors you hire pull their own permits tied to yours.
  • Under section 489.103, Florida Statutes, selling or leasing within one year of completion creates a presumption you built it for sale or lease.

Read our owner-builder permit guide on the liability you take on first.

When do I need a Notice of Commencement in Duval County?

You need one when the direct contract is over $5,000, under section 713.135, Florida Statutes. A contract to repair or replace an existing heating or air-conditioning system for less than $15,000 is excluded.

A Notice of Commencement (NOC) is a document the owner records so subcontractors and suppliers know who to notify about payment. Jacksonville requires a copy of the recorded NOC before you request any inspection. You can record it at the Clerk of Courts, 501 W. Adams St., or at the clerk's office inside the Building Inspection Division at 214 N. Hogan St. Our Notice of Commencement guide explains each field.

How do shed permits work in Jacksonville?

Owner-obtained shed permits start in person at the Ed Ball Building. Bring a photo ID and a survey-based site plan showing the shed's distance from at least two property lines.

Size and cost thresholds

  • Sheds under 150 square feet and under $5,000 are issued during your visit and often need no inspection.
  • Sheds of 150 square feet or more need structural drawings signed and sealed by a Florida licensed design professional, plus product approval sheets, and go to plan review.
  • Shed jobs costing $5,000 or more need a recorded Notice of Commencement.

How do inspections work in Jacksonville?

You schedule inspections through JaxEPICS or by calling 904-255-8500 on workdays from 7 a.m. to 4 p.m., and they are scheduled for the next business day. The permit and Notice of Commencement must be posted at the job site before any inspection.

The approved plans must be on site in a weatherproof container, and an occupied home needs someone 18 or older present. You can also look up past permits, certificates of occupancy, and violations through the JaxEPICS property search using its guest sign-in, which is useful before you buy a home.

What happens if I start work without a permit?

Jacksonville says starting work without first applying for a permit is unlawful and punishable by a $250 fine. The city also warns that failing to get required inspections can result in a property lockdown that blocks future permits at your address.

Jacksonville flags warning signs of an unlicensed contractor, including being asked to pull the permit yourself or being told the job needs no permit. Verify any license with the Florida Department of Business and Professional Regulation.

Our take: In Duval County, settle the jurisdiction first, then assume the job needs a permit until the office tells you otherwise. Window, roof, and shed work all have their own published rules here, and an unpermitted job tends to surface at sale, refinance, or after a storm.

How do permits work in the Duval beach cities and Baldwin?

Each of the four municipalities runs its own process, so apply directly to the city or town, not to Jacksonville.

Jacksonville Beach

The city's Building Inspection Division issues permits and takes e-permit applications on its website, including window and door and roof applications. Construction is allowed 8 a.m. to 6 p.m., Monday through Saturday.

Atlantic Beach

The Building Division uses BSAOnline, with a separate application link for property owners, and posts a July 2026 fee update.

Neptune Beach

The city lists windows, skylights, garage doors, water heater replacements, fences, sheds, roofing, and decks among work that needs a permit, and building permits generally need documentation of 130 mph wind code compliance. Call 904-270-2400.

Baldwin

Jacksonville identifies the Town of Baldwin as running its own building and zoning enforcement, so contact the town before you start.

A homeowner on a sunny Jacksonville Beach street looking up at new roofing on a coastal cottage

What should I do before starting a project in Duval County?

Confirm your jurisdiction, then the permit, fees, and paperwork, before you sign a contract.

  • Check the city line. If you are not in Jacksonville Beach, Atlantic Beach, Neptune Beach, or Baldwin, Jacksonville's Building Inspection Division is your office.
  • Verify your contractor's license with the state before paying a deposit.
  • Plan the Notice of Commencement for any contract over $5,000.
  • Ask about the $7,500 exemption only for small, non-structural work outside a flood hazard area.

When you are ready, check your project in our free tool, then confirm every detail with your building department.

Frequently asked questions

Does Duval County or the City of Jacksonville issue building permits?
Jacksonville and Duval County are a consolidated government, so the City of Jacksonville's Building Inspection Division issues permits for most of the county. The city says its division's authority is limited to the City of Jacksonville, and that the City of Jacksonville Beach, the City of Atlantic Beach, the City of Neptune Beach, and the Town of Baldwin run their own building and zoning enforcement. If your property is in one of those four, apply to that city or town.
How do I apply for a building permit in Jacksonville?
Jacksonville requires online submission for all permit types through its JaxEPICS system, and you need a JaxEPICS account to submit. Applications move through Development Services review, any agency reviews, a sufficiency review, and plan review before the permit becomes active. Homeowners pulling an owner-builder permit for a shed start in person at the Building Inspection Division, 214 North Hogan Street.
How much does a window replacement permit cost in Jacksonville?
Jacksonville's published fee for window and door replacement is a permit fee of $4.00 per $1,000 of construction cost plus a $25.00 C&D fee per permit, with a $150.00 minimum permit fee when the permit requires one or more inspections. These figures were checked in November 2026 on the city's City Fees page, which prints no effective date, so confirm before you budget.
What wind speed applies to my Jacksonville home?
Jacksonville sets a wind speed line by ordinance. It runs up the middle of the St. Johns River from the south end of Duval County to Interstate 95 at the Fuller Warren Bridge, then north along I-95 to the county line. For Risk Category II structures, which covers typical homes, the wind speed is 125 mph west of the line and 130 mph east of it.
Can a homeowner pull their own permit in Jacksonville?
Yes, for your own primary residence if it is not for sale or rent and your name is on the deed. Jacksonville requires you to appear in person at the Building Inspection Division and sign an Owner's Affidavit, and improvements to an existing structure also need proof of Homestead Exemption. Licensed electrical, plumbing, mechanical, and roofing contractors you hire still pull their own permits.
When is a Notice of Commencement required in Duval County?
Under section 713.135, Florida Statutes, the permit office requires a copy of the recorded Notice of Commencement before the first inspection when the direct contract is over $5,000. A contract to repair or replace an existing heating or air-conditioning system for less than $15,000 is excluded. Jacksonville requires the recorded copy before you request any inspection.
How long does plan review take in Jacksonville?
Jacksonville's FAQ says to expect 25 to 30 business days for the first review of a building permit because of current volume, and about 10 business days or less for resubmissions. The review clock does not start until Zoning, Concurrency, and Development Services have approved the plans for review and the plan review fee is paid. Contact your plans examiner for current timing.

Sources

See what your project actually needs

Run the free check for your project and jurisdiction. Every result links back to its official source.