Do I need a permit for roof replacement or repair in Orlando?

Permit required

Yes. In Florida, roof replacement or repair generally requires a permit, and Orlando is no exception.

Florida requires a permit to replace or recover a roof, and most repairs above a small area also need one. Under the Florida 25 percent rule, if 25 percent or more of a roof section is repaired or replaced within 12 months, that section must be brought up to the current Florida Building Code. The roofing system usually needs Florida Product Approval.

Local and county notes for Orlando

Florida requires a permit to replace or recover a roof covering. Homes in wind-borne debris regions face added roof-to-wall and secondary-water-barrier requirements. Small isolated repairs below a local threshold are sometimes handled without a permit, but that is a local decision. Once 25 percent or more of a roof section is repaired within 12 months, that section must meet current code and needs a permit. Orlando reinstated the dry-in inspection (code 125) as of January 1, 2020. A re-roof permit that skips the dry-in inspection may be disapproved at final, and the city can require removing part or all of the roof covering to inspect the underlayment and sheathing nailing. Roofing products must meet Florida Product Approval statewide even though Orlando is inland and not in a High Velocity Hurricane Zone. The city reviews the roof covering, underlayment and fastener details on the re-roofing form. Apply online and download the approved permit from ProjectDox at digitalpermits.orlando.gov. A permit left open for six months with no inspection will expire. Orange County's own permitting office is the Orange County Permitting Services, Division of Building Safety, reachable on 407-836-5550 at https://www.orangecountyfl.net/PermitsLicenses/Permits.aspx. Its online permit portal is https://fasttrack.ocfl.net/OnlineServices/. It issues permits for the unincorporated county. If your city does not run its own building department, and many smaller Florida municipalities do not, this is the office that will handle the job. Roofing permits and the dry-in inspection are handled by whichever office serves your address, and Florida requires product approval documentation for roof coverings.

Documents you may need

  • Permit applicationLikely required
  • Licensed roofing contractor informationSometimes required
  • Product approval (FL number or NOA) for the roofing systemLikely required
  • Notice of commencement (for work over the statutory value)Sometimes required
  • Permit application (if above the local repair threshold)Sometimes required
  • Residential re-roofing form (estimated cost, roof covering, underlayment and fastener details)required
  • Owner/Builder Declaration, signed in person at the Permitting Services office, if you are doing the work yourself instead of hiring a contractorSometimes required
  • Recorded Notice of Commencement (required when the value of the work exceeds $5,000)Sometimes required
  • Completed roofing inspection affidavit for the final inspection (roof decking nailing and secondary water barrier)required

Possible inspections

  • Sheathing and nailing inspection
  • Dry-in (underlayment) inspection
  • Final inspection
  • Dry-in / in-progress inspection (inspection code 125), reinstated by the city as of January 1, 2020, for all residential re-roof projects
  • Final roof inspection, which requires the completed inspection affidavit verifying decking nail-down and secondary water barrier

Frequently asked questions

Do I need a permit for roof replacement or repair in Orlando?
Yes. In Florida, roof replacement or repair generally requires a permit, and Orlando is no exception. Florida requires a permit to replace or recover a roof, and most repairs above a small area also need one. Under the Florida 25 percent rule, if 25 percent or more of a roof section is repaired or replaced within 12 months, that section must be brought up to the current Florida Building Code. The roofing system usually needs Florida Product Approval.
Who issues the permit in Orlando?
The local building department for Orlando handles permitting. This page lists its contact details and online portal. Your mailing city is not always the permitting authority, so confirm the jurisdiction before you apply.
How do I find out the exact requirements for my project?
Run the free PermitRoadmap check for your specific project and answers. It returns the likely permits, documents, inspections, and next steps, each linked to its official source.

PermitRoadmap is an independent informational service and is not affiliated with any city, county, state agency, or permitting authority. Results are informational and do not replace confirming requirements with the local permitting authority.