Do I need a permit for solar panel installation in Unincorporated Custer County?

Unincorporated Custer County does not issue residential building permits. Custer County states that it currently has no zoning or building codes, so the county does not issue building permits. Its Planning Department still handles septic (on-site wastewater) permits, road approach permits, floodplain rules under Ordinance #6 and 911 addressing. Work inside the City of Custer or Hermosa should be checked with that town.

The requirements below come from South Dakota rules and describe the standard the work must still meet. They are not a statement that Unincorporated Custer County will issue you a permit.

Permit required

Yes. In South Dakota, solar panel installation generally requires a permit, and Unincorporated Custer County is no exception.

A generating system connected in parallel with the power supplier must have a state wiring permit and must be jointly approved by the power supplier and the Electrical Commission (ARSD 20:44:25:02, 20:44:25:09). A grid-tied system must disconnect automatically when the power supplier's system is de-energized, using backfeed equipment approved by the supplier and the commission (ARSD 20:44:25:08). Solar easements to protect sun exposure are voluntary written agreements recorded with the register of deeds; we found no South Dakota statute limiting homeowners association rules on solar panels (SDCL 43-13-16.1, 43-13-17).

Get your exact answer

Answer a few questions to see the specific permits, documents, and next steps for your solar panel installation in Unincorporated Custer County.

Check my project

Documents you may need

  • State wiring permit from the South Dakota Electrical Commission (or Rapid City or Sioux Falls inside city limits)Required
  • Power supplier interconnection approvalRequired
  • System design with equipment listings and disconnect locationsLikely required
  • Building permit for roof or ground mounting, where the city or county enforces a building codeSometimes required

Possible inspections

  • State or local electrical inspection of the system and disconnects
  • Power supplier review before the system operates in parallel with the grid
  • Structural or final inspection where a building permit applies

Frequently asked questions

Do I need a permit for solar panel installation in Unincorporated Custer County?
Yes. In South Dakota, solar panel installation generally requires a permit, and Unincorporated Custer County is no exception. The documents and inspections sections on this page list what the building department typically asks for.
Who issues the permit in Unincorporated Custer County?
The local building department for Unincorporated Custer County handles permitting. This page lists its contact details and online portal. Your mailing city is not always the permitting authority, so confirm the jurisdiction before you apply.
How do I find out the exact requirements for my project?
Run the free PermitRoadmap check for your specific project and answers. It returns the likely permits, documents, inspections, and next steps, each linked to its official source.

PermitRoadmap is an independent informational service and is not affiliated with any city, county, state agency, or permitting authority. Results are informational and do not replace confirming requirements with the local permitting authority.