Do I need a permit for solar panel installation in Unincorporated Big Stone County?

Unincorporated Big Stone County does not issue residential building permits. Per the Minnesota DLI State Building Code Jurisdiction Directory (https://workplace.doli.state.mn.us/jurisdiction/, search county Big Stone), no township or unorganized territory in Big Stone County has adopted the State Building Code, so no building code permit or inspection is issued for homes outside cities. The county zoning office issues the required zoning/land use permit (setbacks, shoreland, septic). State electrical permits come from DLI; plumbing follows state rules. The county Environmental Office requires permits outside city limits for all new construction under the county zoning ordinance.

The requirements below come from Minnesota rules and describe the standard the work must still meet. They are not a statement that Unincorporated Big Stone County will issue you a permit.

Permit required

Yes. In Minnesota, solar panel installation generally requires a permit, and Unincorporated Big Stone County is no exception.

A solar photovoltaic system is a new electrical installation that must be inspected under Minn. Stat. 326B.36, by DLI or by the city where a local electrical inspection program exists. Roof-mounted arrays also need a building permit in jurisdictions that enforce the State Building Code; Minn. R. ch. 1325 covers solar thermal systems, not photovoltaic panels. Utility interconnection and net metering are governed by Minn. Stat. 216B.164 and the utility's approved process, separate from the permit.

Get your exact answer

Answer a few questions to see the specific permits, documents, and next steps for your solar panel installation in Unincorporated Big Stone County.

Check my project

Documents you may need

  • Electrical permit (request for electrical inspection) filed with DLI or the local electrical authorityrequired
  • Property address and parcel informationrequired
  • Electrical one-line diagram and equipment specificationsLikely required
  • Building permit with roof structural information where the jurisdiction enforces the building codeLikely required
  • Utility interconnection application or agreementLikely required

Possible inspections

  • Electrical rough-in inspection where wiring will be concealed
  • Final electrical inspection before the system is energized
  • Structural or building final inspection where a building permit is issued

Frequently asked questions

Do I need a permit for solar panel installation in Unincorporated Big Stone County?
Yes. In Minnesota, solar panel installation generally requires a permit, and Unincorporated Big Stone County is no exception. The documents and inspections sections on this page list what the building department typically asks for.
Who issues the permit in Unincorporated Big Stone County?
The local building department for Unincorporated Big Stone County handles permitting. This page lists its contact details and online portal. Your mailing city is not always the permitting authority, so confirm the jurisdiction before you apply.
How do I find out the exact requirements for my project?
Run the free PermitRoadmap check for your specific project and answers. It returns the likely permits, documents, inspections, and next steps, each linked to its official source.